Hawke Street is a wide paved road that runs between Railway Place and Victoria Street in an area that is transitioning from a commercial precinct to a mixed-use neighbourhood, with a rapidly growing population.

With this change comes an opportunity to redefine the street’s character with new trees, green landscaping, bike lanes and pedestrian paths.

The Hawke Street greening project is a key initiative of the West Melbourne Structure Plan (2018). It seeks to reduce through-traffic and mitigate increased vehicle flow from the West Gate Tunnel, improve bicycle and pedestrian connectivity, and increase green space, making Hawke Street a better place to live and sustainably commute.

From 8 December 2025 to 8 February 2026, we consulted the community on two concept design options. A refined version of option 2 and was endorsed by the Future Melbourne Committee on Tuesday 19 May 2026. You can find out more about the engagement, as well as the consultation phases we undertook in 2021 and 2022 below.

The project will now move through a detailed design process, with construction expected to begin in early 2027.

Hawke Street greening is co-funded by City of Melbourne and the Department of Transport and Planning through the Transport Amenity Program (TAP).

Community consultation

Feedback we heard during engagement on the Hawke Street greening project.

Timeline

  • Timeline item 1 - complete

    Community consultation on preliminary concept plan

    26 March to 25 April 2021

  • Timeline item 2 - complete

    Feedback collated and reviewed

    Mid 2021

  • Timeline item 3 - complete

    Concept Plan endorsed by Councillors for further consultation

    Nov 2021

  • Timeline item 4 - complete

    Community workshop to test and refine designs

    December 2021

  • Timeline item 5 - complete

    Community consultation on new concept plan

    20 December 2021 to 18 January 2022

  • Timeline item 6 - complete

    Design/development/documentation

    2023

  • Timeline item 7 - complete

    Concept design endorsed by Future Melbourne Committee

    May 2023

  • Timeline item 8 - complete

    Design development and project planning

    2024 to 2025

  • Timeline item 9 - complete

    Community consultation

    8 December 2025 to 8 February 2026

  • Timeline item 10 - complete

    Recommended design option endorsed by Future Melbourne Committee

    Tuesday 19 May 2026

  • Timeline item 11 - incomplete

    Works commence

    Early 2027