The University Square Master Plan sets the direction to transition a 19th century landscape into a modern space that will provide more room for the community and complement a range of future uses, while recognising the rich history of the site.
The Master Plan was endorsed in 2016 and outlines a vision for the Square that will better serve the local community, students, workers and visitors.
Stage one was completed in 2019, creating a large new open space, additional trees, a biodiverse garden, seating and terrace spaces.
With Parkville Station now open, stage two works (endorsed by the Future Melbourne Committee on Tuesday 23 April 2024) will commence in early 2026. These works align with the updated 2016 Master Plan, which responds to the changes the Metro Tunnel will deliver to Carlton, and a detailed design process, which included community consultation on the draft design in late 2023.
Site set up activities are due to commence in late-January. Construction is expected to commence in February 2026 and be completed by the end of 2026. For the latest information about this project, including the impacts while works are underway, visit the University Square Master Plan page. See the endorsed master plan below.
Endorsed by Future Melbourne Committee on 23 April 2024
Consultation closed
Timeline
-
Timeline item 1 - complete
Community consultation on the University Square Master Plan and Stage One design plan
2014 to 2016
-
Timeline item 2 - complete
Stage 1 - What's your vision community engagement
1 September to 13 October 2014
-
Timeline item 3 - complete
Review community feedback and develop ideas plan
October 2014 to January 2015
-
Timeline item 4 - complete
Stage 2 - Ideas plan community engagement
16 January to 11 March 2015
-
Timeline item 5 - complete
Review community feedback on ideas plan and develop draft master plan
March to August 2015
-
Timeline item 6 - complete
Stage 3 - Draft Concept Plan community engagement
25 August to 5 October 5 2015
-
Timeline item 7 - complete
Review Concept Plan feedback and prepare draft Master Plan
October 2015 to July 2016
-
Timeline item 8 - complete
Draft Master Plan released for feedback
26 August to 19 September 2016
-
Timeline item 9 - complete
Master Plan presented to Council and adopted
December 2016
-
Timeline item 10 - complete
Master Plan implementation
October 2017 to May 2018
-
Timeline item 11 - complete
Parkville Station (Metro Tunnel) construction commences
2018
-
Timeline item 12 - complete
Stage 1 open to public
2019
-
Timeline item 13 - complete
Temporary artwork by Sean Lynch installed
2021
-
Timeline item 14 - complete
MPavilion installed on site
2022
-
Timeline item 15 - complete
Master Plan Refresh commences
2023
-
Timeline item 16 - complete
Engagement on Stage Two draft concept design
5 October to 20 November 2023
-
Timeline item 17 - complete
Integrate engagement findings into final concept design and present to community
Early 2024
-
Timeline item 18 - complete
University Square Stage 2 Concept Design endorsed by the Future Melbourne Committee
23 April 2024
-
Timeline item 19 - active
Works to begin, following detailed design process on Stage 2 Concept Design
January 2026