The University Square Master Plan sets the direction to transition a 19th century landscape into a modern space that will provide more room for the community and complement a range of future uses, while recognising the rich history of the site.

The Master Plan was endorsed in 2016 and outlines a vision for the Square that will better serve the local community, students, workers and visitors.

Stage one was completed in 2019, creating a large new open space, additional trees, a biodiverse garden, seating and terrace spaces.

With Parkville Station now open, stage two works (endorsed by the Future Melbourne Committee on Tuesday 23 April 2024) will commence in early 2026. These works align with the updated 2016 Master Plan, which responds to the changes the Metro Tunnel will deliver to Carlton, and a detailed design process, which included community consultation on the draft design in late 2023.

Site set up activities are due to commence in late-January. Construction is expected to commence in February 2026 and be completed by the end of 2026. For the latest information about this project, including the impacts while works are underway, visit the University Square Master Plan page. See the endorsed master plan below.

Consultation closed

Timeline

  • Timeline item 1 - complete

    Community consultation on the University Square Master Plan and Stage One design plan

    2014 to 2016

  • Timeline item 2 - complete

    Stage 1 - What's your vision community engagement

    1 September to 13 October 2014

  • Timeline item 3 - complete

    Review community feedback and develop ideas plan

    October 2014 to January 2015

  • Timeline item 4 - complete

    Stage 2 - Ideas plan community engagement

    16 January to 11 March 2015

  • Timeline item 5 - complete

    Review community feedback on ideas plan and develop draft master plan

    March to August 2015

  • Timeline item 6 - complete

    Stage 3 - Draft Concept Plan community engagement

    25 August to 5 October 5 2015

  • Timeline item 7 - complete

    Review Concept Plan feedback and prepare draft Master Plan

    October 2015 to July 2016

  • Timeline item 8 - complete

    Draft Master Plan released for feedback

    26 August to 19 September 2016

  • Timeline item 9 - complete

    Master Plan presented to Council and adopted

    December 2016

  • Timeline item 10 - complete

    Master Plan implementation

    October 2017 to May 2018

  • Timeline item 11 - complete

    Parkville Station (Metro Tunnel) construction commences

    2018

  • Timeline item 12 - complete

    Stage 1 open to public 

    2019

  • Timeline item 13 - complete

    Temporary artwork by Sean Lynch installed

    2021

  • Timeline item 14 - complete

    MPavilion installed on site

    2022

  • Timeline item 15 - complete

    Master Plan Refresh commences

    2023

  • Timeline item 16 - complete

    Engagement on Stage Two draft concept design

    5 October to 20 November 2023

  • Timeline item 17 - complete

    Integrate engagement findings into final concept design and present to community

    Early 2024

  • Timeline item 18 - complete

    University Square Stage 2 Concept Design endorsed by the Future Melbourne Committee

    23 April 2024

  • Timeline item 19 - active

    Works to begin, following detailed design process on Stage 2 Concept Design

    January 2026

Contact us

Have questions or want to learn more about the project?