Community Consultation - Phase 1
Phase 1: Feedback we heard on the Draft Greenline Implementation Plan
The Greenline Project is a transformational project that presents a new vision for the north bank of the Yarra River - Birrarung. It will create 4km of interconnected promenades, parks, open spaces, Australian native planting, cultural activations and environmental renewal between Birrarung Marr and the Bolte Bridge.
The project is underpinned by policies and strategies prepared by Council and the State Government. These reference Traditional Owner culture and heritage together with community aspirations to improve the health and wellbeing of the river, with new promenades, public space, and improved connections.
The Greenline Project is located on the lands of the Wurundjeri Woi-wurrung people, and guidance from Traditional Owners will be ongoing throughout the design and development of this project.
The final Greenline Project Master Plan was approved by the Future Melbourne Committee on 5 December 2023.
The master plan will provide a framework for the Greenline Project, one of the biggest city-shaping projects in Melbourne’s history.
We integrated feedback from a four-week stakeholder and community engagement program into this Master Plan. Feedback will be used to develop and refine future Precinct Plans and Concept designs.
Read the Greenline Project Phase 4 Community consultation summary.
Follow this page to receive email updates.
Timeline item 1 - complete
Yarra River – Birrarung Strategy endorsed by Council’s Future Melbourne Committee
December 2019
Timeline item 2 - complete
Draft Greenline Implementation Plan endorsed by Council’s Future Melbourne Committee
May 2021
Timeline item 3 - complete
Community consultation on Draft Greenline Implementation Plan
23 August to 3 October 2021
Timeline item 4 - complete
Greenline Implementation Plan endorsed by Council’s Future Melbourne Committee
7 December 2021
Timeline item 5 - complete
Commencement of sensor implementation, starting with Birrarung Marr
December 2021
Timeline item 6 - complete
Community consultation on The Greenline Project precinct planning, and Birrarung Marr Precinct Site One (Phase 2 engagement)
2 August to 12 September 2022
Timeline item 7 - complete
Birrarung Marr Precinct Site One concept plan endorsed by Council’s Future Melbourne Committee
December 2022
Timeline item 8 - complete
Installation of Trial Floating Wetlands in three sites along the central city waterways
December 2022 to March 2023
Timeline item 9 - complete
Community consultation to inform The Greenline Project Master Plan (Phase 3 engagement)
5 April to 17 May 2023
Timeline item 10 - complete
Preparation of draft Greenline Project Master Plan for council endorsement
Mid 2023
Timeline item 11 - complete
Community consultation on the draft Greenline Project Master Plan
16 August to 13 September 2023
Timeline item 12 - complete
Final Greenline Project Master Plan for endorsement by Council
Late 2023
Timeline item 13 - incomplete
Birrarung Marr Precinct Site One to commence construction
2024
Timeline item 14 - active
Community and key stakeholder engagement throughout the life of the project
Ongoing
The Greenline Project Draft Master Plan incorporates feedback from the recent Informing the Greenline Project Master Plan consultation. This builds on previous engagement for the Greenline Implementation Plan in 2021, and consultation in 2022 on Precinct Planning and the draft Concept Design for the Birrarung Marr Precinct Site 1 project.
For further information on previous community engagement, see below.
Phase 1: Feedback we heard on the Draft Greenline Implementation Plan
Phase 2: Feedback we heard on The Greenline Project and the Draft Concept Plan for Birrarung Marr Precinct Site One
Phase 3: Feedback we heard on Informing the Greenline Project Master Plan.
Phase 4: Feedback we heard on the Greenline Project Draft Master Plan.
Seafarers Rest is an existing public open space earmarked for renewal in the City of Melbourne’s Open Space Strategy. It has also been identified as a key area in the Docklands Public Realm Plan.
The Greenline Project was one of the actions to come out of the Yarra River - Birrarung Strategy, which was endorsed in 2019.
Engagement on the Draft Greenline Implementation Plan took place end of 2021. Learn more about the bold vision and what we heard from the community.
The Greenline Project Draft Master Plan outlines a vision for transforming the north bank of the Yarra River – Birrarung.